Here\u2019s the good news: Honolulu rail officials won\u2019t have to replace entire track crossings along the island\u2019s elevated transit route in order to fix the problems with ill-fitting train wheels.<\/a><\/p>\n
That combined approach has been blessed by TTCI<\/a>, the railroad expert hired earlier this year to examine the problem, in the firm\u2019s recent report for the Honolulu Authority for Rapid Transportation.<\/p>\n
That likely means further<\/a> delay<\/a> to provide interim rail service, an effort that\u2019s already faced numerous setbacks. Currently, HART hopes to deliver the transit line\u2019s first 10 miles from east of Kapolei to Aloha Stadium by mid-2022, according to agency officials.<\/p>\n
HART\u2019s schedule calls for the temporary welding to be done by mid-November but it\u2019s \u201cvery, very likely\u201d that won\u2019t happen, HART Project Manager Nathaniel \u201cNate\u201d Meddings told agency board members during a project oversight meeting<\/a> Tuesday.<\/p>\n
A solicitation for the welding work failed to draw any bidders<\/a> by the September deadline. HART officials later said that was because no companies in Hawaii were licensed to do the welding work.<\/p>\n
The steel wheels on Honolulu\u2019s four-car trains are currently 4.75 inches wide, according to TTCI\u2019s Oct. 22 report, which Civil Beat obtained through a public records request.<\/p>\n
Previously, the agency had refused to clarify the status of that report<\/a> and whether TTCI had delivered it.<\/p>\n
Hitachi\u2019s 2011 core systems contract<\/a> states that the company \u201cshall finalize the (wheel) profile and retain final responsibility for obtaining satisfactory wheel\/rail interface performance and minimum rail\/wheel wear rates.\u201d<\/p>\n