Grabauskas: Honolulu Rail Audit ‘A Mess’
UPDATED: A draft copy says HART contributed to cost overruns with poor management. HART’s head says it’s flawed by political motivations.
HART Board Chairman Resigns Amid Questions About Rail Cost Overruns
UPDATED: Don Horner says he hopes his departure will help build a better relationship between the rail agency and the city.
Rail Vote Suit Dismissed, Appeal Likely
An ethics scandal called into question more than 100 votes cast by Honolulu City Council members, some of which involved the city’s $6.6 billion rail project.
Civil Beat Poll: Only 16 Percent Of Voters Feel Good About Honolulu Rail
Well over 30聽percent of respondents said it鈥檚 a bad idea while another 40 percent consider the $6.6 billion project’s progress troubling.
Caldwell Signs Honolulu Rail Tax Extension
The city’s $6.6 billion commuter rail line, which is currently under construction,聽is already over budget and behind schedule.
Honolulu City Council Approves Rail Tax Extension
The extra tax money will go toward paying for cost overruns and revenue shortfalls on the $6.6 billion project.
Tax Extension Revenue For Honolulu Rail Chugs Ahead
The Honolulu City Council聽Budget Committee placed a $1.1 billion cap on spending, although it allowed for some leeway should those funds not be enough.
Five Unanswered Questions About Honolulu’s $6.6 Billion Rail Project
Even as City Council members decide whether to keep the cash flowing, uncertainty looms over Hawaii’s biggest public works endeavor.
HART OKs New Contract For Rail Stations
The聽apparent low bidder to build stations at Aloha Stadium, Pearl Ridge and Pearl Highlands did not meet HART specifications.
What Could $1.5 Billion Buy You (Besides More Of The Rail Project)?
The Honolulu City Council is weighing extending the general excise tax surcharge by five more years to raise $1.5 billion more for rail.聽But what else could all that money pay for?