HART, trying to manage public expectations, wanted to keep that target vague.
The top executive overseeing construction of Honolulu鈥檚 rail project was surprised to learn moments before last month鈥檚 annual State of the City address that Mayor Rick Blangiardi would declare the transit system鈥檚 first leg ready to ride in July.
鈥淭he split second before he came out, he said 鈥楯uly,鈥 and I gasped because we expected him to say 鈥榮ummer,鈥欌 Honolulu Authority for Rapid Transportation Executive Director Lori Kahikina said Monday on the Honolulu Star-Advertiser鈥檚 辫谤辞驳谤补尘.听
鈥淏ut that鈥檚 OK 鈥 he put that stake in the ground. He is a dynamic leader and coach,鈥 Kahikina said.
Kahikina further revealed that Blangiardi had told her two days prior to his March 14 speech that he actually wanted to declare the rail system would be ready to ride in a month.
鈥淎nd we鈥檙e saying, no please – HART鈥檚 reputation. We don鈥檛 want to overpromise (and) underdeliver, so just say 鈥榮ummer,鈥欌 Kahikina recounted on Spotlight. 鈥淛ust be a little bit vague 鈥 because this is a major infrastructure project. Anything can go wrong.鈥
Blangiardi reluctantly agreed to go with summer, she said. Kahikina then learned of the change right before he went on stage.
鈥淲e are ready for riders to embrace rail,鈥 Blangiardi . 鈥淥ur long-awaited rail system is scheduled to commence interim operations in July.鈥
Immediately following the speech, Kahikina said, she sent an agency-wide email out to HART staff saying they would meet the mayor鈥檚 July target.
鈥淲e鈥檙e not going to make a liar out of him, so let鈥檚 get this done,鈥 Kahikina said, recounting the email to staff. 鈥淲e鈥檙e going to hit that July deadline for mayor and the community.鈥
Kahikina shared that glimpse into how the city arrived at its latest, July target after the Spotlight hosts asked if she was confident the rail鈥檚 first 10 miles, from east Kapolei to Aloha Stadium, would be ready to ride by then.
A Moving Target
For years, city elected leaders and transportation officials have been anxious to launch partial service of Oahu鈥檚 elevated rail line.
The move, they hope, will help improve public perception and spur interest in Hawaii鈥檚 largest-ever infrastructure project, whose price tag has more than doubled and whose completion date has been pushed back about a decade.
However, some critics – including some rail industry experts 飞丑辞鈥檝别 worked on the project 鈥 say the aggressive push to get rail鈥檚 first half open has led to some questionable construction decisions, including the methods that HART used to address problems with its track crossings and tolerances.
Nonetheless, Kahikina told “Spotlight Hawaii” on Monday that HART and Hitachi, the company that will operate rail for the city, have successfully completed the system鈥檚 critical trial-running phase. That phase included 144 test scenarios and a system demonstration that Hitachi finished weeks ahead of schedule, on April 2, according to Kahikina.
HART further expects to have all of the diagonal 鈥渟hear鈥 cracks causing concerns in the so-called 鈥渉ammerhead piers鈥 that line rail鈥檚 western half repaired by the end of May, Kahikina told Spotlight.
HART officials have kept the public up to speed on those repairs, but they鈥檝e offered few details into what might have caused the shear cracks in the first place.
Sign up for our FREE morning newsletter and face each day more informed.
Support Independent, Unbiased News
Civil Beat is a nonprofit, reader-supported newsroom based in 贬补飞补颈驶颈. When you give, your donation is combined with gifts from thousands of your fellow readers, and together you help power the strongest team of investigative journalists in the state.
About the Author
-
Marcel Honor茅 is a reporter for Civil Beat. You can email him at mhonore@civilbeat.org