The wheels on Honolulu’s struggling rail project might literally be coming off soon.
Project officials shed more light Thursday on the 鈥渕ajor鈥 and costly problem that鈥檚 emerging with the system鈥檚 train car wheels, a snafu they say could delay the elevated rail line鈥檚 interim opening by another year.
The wheel flanges, or rims, on the Hitachi Rail-manufactured cars are too narrow, they said, affecting the driverless trains鈥 ability to safely navigate certain track crossings at the speeds needed to operate on schedule.
HART learned of the problem in either late December or early January when crews discovered early wear on the track crossings, called 鈥渇rogs,鈥 according to briefings by HART Deputy Director for Engineering and Design In-Tae Lee and Bob Good, HART鈥檚 senior project officer.
The trains had been doing test runs for about a year at that point on the elevated track over Farrington Highway in Waipahu.
The agency’s subject-matter experts then determined that the trains鈥 wheel flanges are about a half of an inch narrower than the frogs, and that impedes the wheels from guiding the trains through the crossing, the two rail officials said. It doesn鈥檛 affect the trains鈥 performance when they鈥檙e moving straight, they added.
鈥淭he variation is so small. It鈥檚 a half-inch, and they really didn鈥檛 notice it until we started to run and they saw a little bit of an unusual wear pattern on the switches,鈥 Good told the board Thursday.
The problem affects at least five crossings on the Westside, and 12 total such crossings planned for the entire 20-mile line to Ala Moana Center.聽 HART was hoping to deliver the first 10 miles to Aloha Stadium to the city later this year to start interim service.
HART and Hitachi are at odds over who鈥檚 responsible and who should pay for it, according to Interim Executive Director Lori Kahikina.
鈥淚t鈥檚 probably going to be a drawn out discussion between us and Hitachi,鈥 Kahikina told the board Thursday. 鈥淥ur stance is, what we have is correct鈥 and that the specifications in the package were properly laid out.
贬颈迟补肠丑颈鈥檚 states that the company 鈥渟hall finalize the (wheel) profile and retain final responsibility for obtaining satisfactory wheel/rail interface performance and minimum rail/wheel wear rates.鈥
It adds: 鈥淚n particular, the vehicle supplier shall verify that the wheel flange dimensions are matched with the flange bearing frogs so as to provide quiet crossing of the frogs with a minimum of impact forces.鈥
After the meeting, HART officials confirmed that鈥檚 the contract language they believe holds Hitachi responsible for the wheel snafu.
It鈥檚 not clear yet how much it will cost to fix the problem. HART is still trying determine whether they can solve it by changing the wheels, although Hitachi has discouraged that approach, Kahikina said. Alternatively, they could replace the frog crossings themselves.
There鈥檚 also minor cracking in the frogs that was found to have occurred during the casting and which can be fixed at nominal cost, she added.
HART also recently found faulty welding along the line that was done about six years ago under the Westside鈥檚 primary construction contractor, Kiewit Infrastructure West, Kahikina told the board. It will cost about $130,000 to fix, and Kahikina said she鈥檚 not sure whether HART has any recourse to recoup that cost from Kiewit since that contract has been closed out, she added.
Reckoning With Higher Costs
Earlier in the meeting, rail officials briefed the board on the mega project’s new, , following major setbacks in 2020.
In recent years, HART aimed to have the project done by 2026. Now, the agency. The extra time needed in that schedule is the main culprit that鈥檚 driven up costs by about $3 billion, said Nathaniel 鈥淣ate鈥 Meddings, who was recently promoted to HART鈥檚 project director.
Previously, he served as project controls director. On Thursday, Meddings and other HART leaders said they鈥檙e trying to better manage public expectations on cost and schedule. 鈥淲e wanted to be as conservatively realistic as possible,鈥 Meddings said after the meeting.
Being more realistic means the new schedule is less aggressive. It adds more time, based on what HART has learned to this point, Meddings said. But the more realistic time frame also drives up the cost.
鈥淲e tried to capture a lot of the known risks on the project,鈥 Meddings added.
HART in previous years has touted risk-management reforms aimed at keeping costs in check, however, so it remains to be seen whether the agency can finally hold the line at its latest price tag.
The schedule also assumes that when contracts are slated to start the city will have the money it needs. The new budget gap is about $3.6 billion.
The over-budget price bids that came in during last year鈥檚 scuttled 鈥淧3鈥 effort also helped inform the new price tag, Meddings said.
The teams that bid weren鈥檛 confident that utilities would be out of the way in time for them to have access to build, and they added 鈥渁 large dollar value鈥 into their prices to cover that risk, he said.
Ironically, the $450 million utility relocation contract that was delaying things had been issued precisely to eliminate such risk and help drive down cost. HART recently canceled that contract, after spending about $100 million of it to get no more than 7% of the utility relocation work done.
Sign up for our FREE morning newsletter and face each day more informed.
Support Independent, Unbiased News
Civil Beat is a nonprofit, reader-supported newsroom based in 贬补飞补颈驶颈. When you give, your donation is combined with gifts from thousands of your fellow readers, and together you help power the strongest team of investigative journalists in the state.
About the Author
-
Marcel Honor茅 is a reporter for Civil Beat. You can email him at mhonore@civilbeat.org