Rail’s Interim Service Could Be Pushed Back A Year Amid COVID-19, Testing Woes
Officials had hoped to deliver rail’s first 10 miles for service this fall. Now they don’t expect that to happen until late 2021.
City transportation officials say they鈥檙e weighing whether to postpone the much-anticipated interim opening of Honolulu rail鈥檚 first 10-miles to Aloha Stadium for another year or so.
鈥淲e鈥檒l be discussing with the next administration,鈥 Acting Department of Transportation Services Director Jon Nouchi told the City Council鈥檚 Budget Committee on Tuesday, referring to Mayor-elect Rick Blangiardi.听
鈥淚t鈥檚 something that we鈥檝e heavily considered.鈥听
The possibility came as the city faces a COVID-19 related budget shortfall of around $400 million, including a shortfall of $40 million to $50 million for transit service, Nouchi said Tuesday. Postponing rail鈥檚 interim opening could help 鈥渟ave a bunch of money鈥 and preserve existing service on TheBus and Handi-Van.
It also followed the disclosure last week by local rail officials that the intensive 90-day trial run required for the driverless trains before they can carry passengers is facing at least an additional four-month delay.
Honolulu Authority for Rapid Transportation officials said Thursday that Hitachi Rail, which is building those trains and the transit line鈥檚 communications systems, informed them of the setbacks the previous week, and that HART didn鈥檛 consider the company to be as 鈥渇orthcoming鈥 as it should have been on the matter.
The testing delays were the latest in a spate of big setbacks that have hampered the 20-mile, 21-station project.
HART Executive Director Andrew Robbins has described rail鈥檚 opening, even in limited capacity, as a critical milestone to reach. The ability of riders to use the service could help change at least some of the negative public perception of the beleaguered transit project and its ballooning costs, he has said.听
Before the pandemic hit, Robbins declared in January that “this is the year” for rail service to finally arrive. His agency aimed to deliver rail鈥檚 western half to the city with the proper safety certifications and 鈥渞eady to ride鈥 in October. City transportation officials will oversee rail鈥檚 operations, as they do with TheBus and Handi-Van, and it鈥檚 up to them to decide when to start that service.
In October, Robbins told the City Council that he expected to have rail .听
Now, amid the testing issues with Hitachi, HART says the earliest it could deliver those first 10 miles to Aloha Stadium will be in July.
Hitachi has been having trouble securing visas during the pandemic for its personnel coming from Italy, according to HART Senior Project Officer Robert Good. That鈥檚 led to 鈥渕anpower鈥 challenges in which some Hitachi workers in Italy have been trying to manage on-site issues on Oahu, Good told the HART board Thursday.听
Hitachi doesn鈥檛 have the licensing it needs to install all of the closed-circuit cameras that will run along the full 10 miles, Good said. That鈥檚 helped push the trial run to April 17, he added, and thus the 90-day trial run would persist through July.
DTS officials say they鈥檙e looking to start rail sometime between next July and December. That would push the launch into the next fiscal year — which is what Nouchi meant, according to an agency spokesman — but still before the end of 2021.
鈥淲e鈥檙e clearly not ready,鈥 outgoing Councilwoman Kym Pine said Tuesday in response to Nouchi鈥檚 testimony. 鈥淲e should focus on survival and current services.鈥
Sign up for our FREE morning newsletter and face each day more informed.
Support Independent, Unbiased News
Civil Beat is a nonprofit, reader-supported newsroom based in 贬补飞补颈驶颈. When you give, your donation is combined with gifts from thousands of your fellow readers, and together you help power the strongest team of investigative journalists in the state.
About the Author
-
Marcel Honor茅 is a reporter for Civil Beat. You can email him at mhonore@civilbeat.org