A new city estimate pushes rail鈥檚 completion date to 2033 and its total price tag, including financing, to around $11 billion.

If that rough estimate holds true it means the troubled transit project鈥檚 cost will have more than doubled since 2012, when Honolulu city leaders signed their funding deal with the federal government, and that its full opening will now be delayed 13 years.

Originally, the 20-mile, 21-station system was supposed to start carrying passengers in 2020 under that with the Federal Transit Administration. But the project has encountered a constant litany of problems since then, including most recently the COVID-19 pandemic and a key utility-relocation effort that completely stalled.

Rail guideway construction at the Daniel K. Inouye International Airport during the COVID-19 pandemic. September 18, 2020
Rail guideway construction at the Daniel K. Inouye International Airport during the COVID-19 pandemic, September 18, 2020 Cory Lum/Civil Beat/2020

In recent months, local rail officials aimed to have the full line ready by fall 2026 but now seemingly no one considers that outcome likely.

The city鈥檚 latest, jarring estimates, which push rail further over budget and behind schedule, were part of a Friday correspondence to the FTA in which Mayor Kirk Caldwell pleaded that Honolulu not lose $250 million of its federal funding. The letter was also sent to Hawaii鈥檚 congressional delegation.

Those dollars are slated to lapse at the end of the year. Caldwell asked for a year’s extension. The FTA is withholding additional federal dollars until the city can demonstrate how it will get the full line as far as Ala Moana from Kapolei.

鈥淟et us reiterate what we have said in our meetings with you over the last eight years: We are so very grateful to the FTA鈥檚 partnership … and your patience with us as we continue to surmount both the challenges of the past and those we confront today,鈥 Caldwell鈥檚 letter read.

鈥淲e are grateful for your steady support.鈥

Honolulu City Councilman Joey Manahan and Toby Martyn, who chairs the Honolulu Authority for Rapid Transportation鈥檚 volunteer board, also signed the letter.

Notably absent from the letter, however, was any input from HART staff or its embattled executive director, Andrew Robbins, highlighting the ongoing rift between city officials and the local rail agency.

鈥淭his plan was developed by the City, without the benefit of the technical expertise and the detailed cost information that is available at HART,鈥 Caldwell鈥檚 letter states. 鈥淗owever, this plan describes what we believe is a reasonable approach to the completion of the project.鈥

Caldwell鈥檚 office did not immediately respond Wednesday on how it developed its new cost and schedule estimates without HART鈥檚 help.

Martyn said that he didn鈥檛 know the methodology either but that he signed the letter because securing the FTA funding remains critical. 鈥淲e鈥檝e got to do everything we can to get those lapsing funds extended,鈥 he said Wednesday.

Robbins and HART staff, meanwhile, presented a separate report to city budget officials Tuesday that asserted the whole project could be completed in late 2027 or early 2028.

Agency spokesman Bill Brennan said that 鈥2033 is not (a) HART number鈥 when asked whether HART agreed with the city鈥檚 later schedule estimate.

Nonetheless, the agency鈥檚 latest budget figures do show the project鈥檚 cost rapidly rising similar to the city鈥檚 estimates.

On Friday, the HART board鈥檚 Finance Committee will review a estimated at nearly $9.9 billion total. That鈥檚 up from the estimate that the agency鈥檚 project control director presented just a month ago and said was sure to increase further.

Neither of those construction figures include the additional $1 billion or so in financing costs, however. HART鈥檚 own estimates aren鈥檛 far off from the city鈥檚 new $11 billion estimate when the financing costs are included.

Robbins continues to press for a novel public-private partnership, or P3, as the best option to get rail done. City leaders, including Caldwell, now strongly disagree. They鈥檝e fiercely lobbied in recent weeks to cancel the ongoing P3 procurement, but Robbins has persisted.

His report Tuesday argued for awarding all of rail鈥檚 remaining major construction under a single contract and then do that work in phases as additional funding becomes available.

Caldwell and the city remain steadfast that the P3 can鈥檛 happen, even if they can鈥檛 provide the justification yet under state procurement rules. The mayor鈥檚 message to the FTA also suggests finishing rail in phases, but it proposes doing that work under separate contracts.

Both HART and the city agree that they need to get a clearer picture of rail鈥檚 latest, massive budget shortfall. It鈥檚 the beleaguered project鈥檚 third major fiscal crisis since 2014.

They鈥檒l also have to find the money to make up the gap.

Read Caldwell’s letter to the FTA here:

Read HART’s report on P3 procurement to the city here:

Support Independent, Unbiased News

Civil Beat is a nonprofit, reader-supported newsroom based in 贬补飞补颈驶颈. When you give, your donation is combined with gifts from thousands of your fellow readers, and together you help power the strongest team of investigative journalists in the state.

 

About the Author