Board members overseeing Honolulu rail fretted Thursday at the latest uncertainties hanging over the state鈥檚 largest-ever public works project.
Two weeks after the city missed its latest deadline, there鈥檚 still no award of the long-anticipated public-private partnership. Rail鈥檚 executive leadership has pursued that deal for the past two years, touting it as an optimal way to complete the project with less risk of added cost to taxpayers.
The so-called 鈥淧3鈥 deal was originally slated to be awarded last September.
鈥淚 think we need to get ahead of things and not be reactive,鈥 Vice Chairman Terrence Lee said Thursday during the Finance Committee鈥檚 latest budget update.
鈥淚 think we need to plan for the possibility that this P3 … is not going to succeed,” he said.
Meanwhile, the elevated project, currently estimated to cost some $9.1 billion, continues to face what HART finance officials estimate will be a $450 million total shortfall in state general excise and hotel tax revenues due to the COVID-19 pandemic.
鈥淗ow are we going to get out of this hole?鈥 Lee asked.
He said he鈥檚 not optimistic the Legislature would bail out rail a third time. He wondered whether rail leaders are simply 鈥減unting鈥 the problem to whomever succeeds Kirk Caldwell as mayor.
鈥淎s far as I know there haven鈥檛 been any serious conversations鈥 about how to cover the shortfall, HART Board Chairman Toby Martyn added.
Martyn said the only option other than the Legislature would be 鈥渇or the city to make up the difference.鈥
Wes Frysztacki, who sits on the HART board as the city鈥檚 transportation director, speculated that the federal government might pass a large-scale relief bill, similar to the CARES Act, that would include funding for major capital projects hit by the pandemic, including rail.
In any case, next year鈥檚 new lineup of city leaders should be briefed on rail鈥檚 issues once the election determines who they鈥檒l be, Lee said.
P3 Progress A Mystery
The P3 deal would have a private firm build the elevated transit line鈥檚 final 4.1 miles and eight stations to Ala Moana Center plus a transit hub and 1,600-space parking garage at Pearl Highlands — work that鈥檚 been valued at $1.4 billion.
It鈥檚 a joint procurement with the city because the deal would also have the firm oversee the elevated rail line鈥檚 first 30 years of operations.
The rail board does not oversee the joint procurement, but it did meet in executive session Aug. 27 to discuss the process.
HART leaders have stayed mum on how that process has gone. An agency panel assigned to evaluate the proposals from private entities submitted its report last month to HART Executive Director Andy Robbins, who serves as the chief procurement officer.
On Thursday, Robbins said HART is taking steps to keep construction on rail moving 鈥渨hether it鈥檚 a P3, (or) whether it鈥檚 a re-procurement.鈥
Scrapping the P3 effort and starting over to procure what鈥檚 known as a standard 鈥渄esign-build鈥 contract would take at least eight months, Robbins said.
Earlier in the meeting, Lee asked HART Chief Financial Officer Ruth Lohr to present them with budget numbers that assume the extra costs and delays associated with a 鈥減lan B鈥 alternative to the P3 award.
鈥淔or a variety of reasons I think we should be planning and adjusting our cash flows on 鈥榩lan B鈥 where we鈥檝e got to re-procure,鈥 Lee said.
It鈥檚 not clear how that re-procurement would impact rail鈥檚 overall completion date, which last month was pushed to April 2026.
It also remains to be seen how the city鈥檚 partners at the Federal Transit Administration would react, as they鈥檝e only agreed to start releasing the remaining $744 million in federal New Starts funds once they see a P3 award that falls within the project鈥檚 budget.
Executive Director’s Contract Under Review
Meanwhile, the HART board鈥檚 Human Resources Committee has met three times in the past two weeks behind closed doors to review Robbins鈥 contract.
The most recent session, on Tuesday, lasted more than an hour. Members opted to continue their discussion next Tuesday.
HART board leaders weren’t available this week to respond to questions seeking more details on why they鈥檙e reviewing Robbins鈥 contract.
However, it appears the board never officially completed its annual review of Robbins鈥 job performance for 2019. Progress on a P3 deal into that evaluation.
In February, the HR committee briefed the full board on its evaluation behind closed doors. The full board agreed with those conclusions, according to Hoyt Zia, who was then serving as the HR committee chair.
The committee was then supposed to go over its review with Robbins and draft a final report. That review with Robbins did eventually take place, but the board never finalized its report, according to HART spokesman Bill Brennan.
Last year, the board discussed its review of Robbins鈥 2018 performance with Robbins鈥 consent, and Robbins shared the final written report.
Sign up for our FREE morning newsletter and face each day more informed.
Support Independent, Unbiased News
Civil Beat is a nonprofit, reader-supported newsroom based in 贬补飞补颈驶颈. When you give, your donation is combined with gifts from thousands of your fellow readers, and together you help power the strongest team of investigative journalists in the state.
About the Author
-
Marcel Honor茅 is a reporter for Civil Beat. You can email him at mhonore@civilbeat.org