COVID-19 is taking its toll on Honolulu rail, threatening to delay even further a $9 billion transit project whose completion was already pushed back at least six years.

Specifically, the global pandemic has further slowed the award for rail鈥檚 last major construction contract, a package that鈥檚 been valued at $1.4 billion.

That so-called public-private partnership to finally get the 20-mile line to Ala Moana and operate the system for 30 years was originally supposed to be awarded in late 2019. The deadline was extended four times, and the latest date was May 15.

Then, the coronavirus hit.

鈥淭here will be a delay,鈥 Executive Director Andrew Robbins told reporters in a conference call Thursday. 鈥淲e were on track.鈥 But due to COVID-19鈥檚 mass-disruption 鈥渁ll of the bidders are having difficulty finalizing their bids.鈥

鈥淭heir ability to put the pricing together involves a lot of interaction with their suppliers, with their subcontractors, and (they) just don鈥檛 have the ability to meet these schedules at this point in time,鈥 he said.

HART Rail Guideway columns near Eliot Street and Daniel Inouye International Airport.
Rail columns run near the Honolulu airport. The COVID-19 crisis has further stalled the award for major construction work past Middle Street. Cory Lum/Civil Beat

It鈥檚 not clear yet whether the virus will impede the city鈥檚 main goal: to deliver the 20-mile, 21-station rail system by December 2025.

鈥淭here is a threat to the date,鈥 Robbins said.

He wouldn鈥檛 say how long HART estimates it would take to award rail鈥檚 long-sought public-private partnership at this point. Robbins plans to brief the agency鈥檚 board next Thursday.

Under rail鈥檚 current master schedule, the project has about 120 days of contingency, or 鈥渇loat,鈥 before the award delay would threaten the December 2025 completion, Robbins said.

Regardless of that schedule, however, HART will now have to discuss with its bidders when they think they could realistically finish construction, he added.

The rail鈥檚 partners at the Federal Transit Administration informed HART almost exactly a year ago that they won鈥檛 release the project鈥檚 remaining $744 million in federal funding until they see the prices of the P3 bids.

On Thursday, Robbins said that HART is already discussing that matter with the FTA and 鈥渨e鈥檙e working on a potential solution with them.鈥

Longer To Ride?

The virus has also pushed back by a month HART鈥檚 goal to have the first 10 miles to Aloha Stadium 鈥渞eady to ride” — the point where it’s passed all the operational tests and received its safety certification.

Robbins had hoped to deliver the rail line鈥檚 western half to the city鈥檚 transportation department in October. Now, HART鈥檚 slated to hand that over at the end of November, Robbins said Thursday.

Multiple work crews have been held up in the state鈥檚 14-day self-quarantine order, including those needed to erect the remaining fabric canopies on west-side stations, he said.

Honolulu Rail HART Train Car
Honolulu’s 20-mile commuter rail project is expected to cost about $9.5 billion. Anthony Quintano / Civil Beat

Meanwhile, the plant that鈥檚 assembling rail鈥檚 driverless trains in Pittsburg, California, was temporarily shut down to deal with the virus, and test engineers for those trains were also held up by the quarantine order, he added.

It鈥檚 not clear whether the city will open rail鈥檚 western half for passenger service on Dec. 20 as planned, once HART hands it over. The city “is carefully weighing all options for future operations, including strong considerations regarding schedule, budget, and workforce,” Department of Transportation Services Deputy Director Jon Nouchi said in an emailed statement Thursday.

Plowing Ahead

Despite those setbacks, the local agency says it鈥檚 trying to take advantage of the island鈥檚 eerily low traffic counts — and lull in local business — to get more of the intrusive construction work out of the way.

Utility relocation crews with the local contracting firm Nan Inc. have ramped up along the usually crowded Dillingham corridor in recent weeks.

Kalihi street has been narrowed to a single lane in either direction between Middle Street and Mokauea Boulevard. HART has dubbed that stretch 鈥1A鈥 in its $400 million effort to get utilities out of the way for future rail columns.

Soon, those Nan crews will creep further east, into section 鈥1B,鈥 Robbins said Thursday.

In January, HART officials reported they were about seven months behind schedule in that utility work, and the agency’s design and construction director said they weren’t moving fast enough. In the agency’s , it said crews had gained three of those months back. With fewer cars on the road, the agency hopes to make up even more time.

Dillingham Boulevard looking towards Costco near Honolulu Community College. Kapalama area.
Work crews have started heavy utility relocation work along Dillingham Boulevard amid the coronavirus lockdown. Cory Lum/Civil Beat

As things stand, the utility work is slated to run through May 2022 and overlap with construction of the rail line itself.

Amid staggering job losses, Hawaii鈥檚 largest public works project has now been classified as an essential infrastructure project. It should help keep at least some employees working and spending in the local economy, Robbins said.

But the $9 billion rail project largely relies on tourism dollars to fund its construction, specifically state general excise and transient accommodation tax revenues. The sector has vanished for the time being, thanks to the coronavirus.

鈥淲e have cash to work with,鈥 but if restrictions persist then 鈥渁t some point this year … we鈥檒l be tapping into our borrowing capacity,鈥 Robbins said.

The rail project relies on the city to float bonds for its financing. HART would have to work with city budget officials and its federal partners to revise its financing plan if the crisis goes on too long, Robbins said.

Support Independent, Unbiased News

Civil Beat is a nonprofit, reader-supported newsroom based in 贬补飞补颈驶颈. When you give, your donation is combined with gifts from thousands of your fellow readers, and together you help power the strongest team of investigative journalists in the state.

 

About the Author