The price to build rail transit stations on Oahu鈥檚 west side continues to soar past the official budget estimates of just a few years ago.

On Thursday, Honolulu Authority for Rapid Transportation board members gave their initial nod to an with Nan Inc., the local firm that鈥檚 building six of the rail line鈥檚 nine westernmost stations.

That deal would resolve about 150 outstanding issues relating to those stations鈥 construction, according to Frank Kosich, HART鈥檚 deputy director for design and construction.

If the full board approves the agreement later this month, it would raise the total change order tally for those nine western stations to nearly $59 million, an increase of about 25% on the original price when their construction contracts were first signed.

鈥淭hat鈥檚 a pretty significant increase,鈥 HART board vice chairman Terrence Lee said Thursday, specifically referring to the trio of stations at the line鈥檚 western end. That trio will see their costs rise by at least $31 million if the resolution with Nan gets final approval.

UH West Oahu HART Rail station entrance.
The future rail station at University of Hawaii West Oahu is part of a trio of west side stations that have seen costs spike by $31 million. Cory Lum/Civil Beat

Lee said that Andrew Robbins, HART鈥檚 executive director, told him that the stations鈥 original budget estimates had been calculated with 鈥渋ncomplete design drawings.鈥

鈥淚t is what it is,鈥 Lee added. 鈥淚t鈥檚 kind of a similar story with why the project went from $5 billion to roughly to $8.1 billion in capital costs.鈥

Indeed, HART officials acknowledged last year that some station design budget estimates were mere 鈥減laceholders鈥 as they approved change orders to nearly double their amount.

The west side stations鈥 costs are almost certain to continue to rise. Kosich said the agreement does not cover all of Nan鈥檚 outstanding claims. He expects to bring to the board a similar resolution agreement with Hawaiian Dredging, the firm building the remaining three west side stations, sometime in the future.

The big cost increases still fall within rail鈥檚 $8.3 billion construction budget, however, and they鈥檙e covered by its contingency fund, officials added.

Much of the cost has to do with the persistent 鈥渋nterface鈥 issues, where the stations鈥 design and the rail line鈥檚 driverless trains, communications and signaling systems didn鈥檛 fit well together.

The surprise discovery of utility lines where they weren鈥檛 supposed to be has also led to hundreds of days of delays — and millions of added dollars in costs. Kosich said he would provide the board a more detailed accounting at the next full board meeting.

HART officials predating Robbins, Kosich and Lee were stunned in 2014 when the lowest bid to build those nine west side stations came in at $294 million — about 60% more than they had estimated.

HART Vice Chair Terrence Lee during board meeting held at Alii Place.
HART Vice Chairman Terrence Lee compared the cost increases for rail’s westside stations to the project’s overall budget overruns. Cory Lum/Civil Beat

In response, they canceled that solicitation and broke the stations up into three sets of three, convinced the move would drive down costs.

At first, the move appeared to work. By November 2015, when the bid to build the final trio of stations was awarded, the price to build all nine stations came in at $250.8 million.

鈥淭he good news, I would say, is I think our staff has finally got our arms around where we see the costs climbing,鈥 HART鈥檚 then-CEO, Dan Grabauskas, .

Since then, however, the costs have soared amid the incomplete designs. In addition to the construction change orders, HART officials approved and added $36 million in guideway and station inspection work.

That was largely needed for San Francisco-based PHG Wong to handle work on all nine stations simultaneously, instead of sequentially, as originally agreed.