For years, the local agency overseeing Honolulu鈥檚 rail construction failed to properly manage dozens of change orders that eventually amounted to nearly half a billion dollars in added costs, a new city auditor鈥檚 report found.
The latest report on rail, released Friday, was conducted last year and mostly covered the Honolulu Authority for Rapid Transportation鈥檚 handling of the project from 2008 to 2016.
Nonetheless, the new report exhaustively chronicles multiple instances during that period in which 鈥渋nexperienced鈥 HART employees approved 鈥渜uestionable鈥 change orders that either lacked necessary documentation, served to improperly cover payments to contractors after the fact, or even violated state procurement law.
鈥淢uch more needs to be done to control project costs and to ensure more schedule delays do not occur,鈥 the city report states.
As with recent similar reports coming out of the state Auditor鈥檚 office, city Auditor Edwin Young鈥檚 office points out that rail鈥檚 federal overseers had repeatedly warned HART that its measures to control and to predict costs weren鈥檛 enough.
鈥淪ince I鈥檝e been here I鈥檝e seen mistakes from the past that have come across my desk. And you know, we have to deal with those now,鈥 HART Executive Director Andrew Robbins said Friday as he addressed the fourth audit released in the past two weeks to scrutinize the agency he leads.
鈥淪ome of the change orders that have come up recently are really closing out some of these issues from two, three years ago or even longer than that,鈥 Robbins said.
鈥淚n some cases I think it could have been avoided,鈥 he added.
Many of the problems originated under Robbins鈥 predecessor, Dan Grabauskas, who resigned as HART鈥檚 executive director under mutual agreement with the board in 2016.
Robbins, who joined HART in September 2017, said the agency has already taken steps to reform its once lax oversight over change orders. The agency created a 鈥渃hange control committee鈥 to review those and determine whether they鈥檙e justified.
鈥淲e鈥檝e added a series of checks and balances, so we鈥檙e doing a much more effective job in terms of change-order processing and risk management,鈥 Robbins said Friday. 鈥淲e鈥檝e achieved good results so far. For the last two years, we have not had an increase on budget at all.鈥
The rail agency further created four new oversight positions to review and approve change orders, according to the city auditor鈥檚 report.
The city auditor HART in 2016, when it faulted the rail agency for and for relying on outdated budgets and financial figures. The report made 16 recommendations to improve HART鈥檚 handling of rail.
At the time, Grabauskas took the unusual step of holding a press conference the day prior to the audit鈥檚 release in order to sharply criticize it and dismiss much of the report as politically motivated.
Rail costs continued to climb steeply, however, and several months later Grabauskas was gone.
‘Questionable’ change orders
To complete its latest report, the city auditor examined the 69 rail contracts that had racked up some 641 cost increases or changes through 2016. Those changes drove the rail project鈥檚 price tag up by more than $488 million, representing a 15 percent increase in the total cost, according to the report.
Those changes added some 2,246 days of work to the rail project鈥檚 schedule, the report stated. The auditor found more than half of the changes to be questionable, with HART staff often ignoring their own internal procedures.
Some change orders lacked the required independent cost estimates.
Others, such as an to cover nine months of delays, lacked any supporting documents whatsoever to detail how that claim was 鈥渘egotiated and justified,鈥 the report said.
In all, some $198 million in contractor invoice payments lacked the necessary documentation or approvals, the report stated.
鈥淚n our view, HART made questionable decisions to override basic internal controls,鈥 it added.
The report looked to shed more light on how the state鈥檚 largest-ever public works project saw its costs balloon from just over $5 billion in late 2014 to more than $9 billion today.
The report only made brief mention of the state and federal lawsuits that in 2012 halted construction for about a year. HART has consistently flagged those lawsuits as a primary reason for the cost increases.
鈥淭hat definitely has an effect when there鈥檚 a year and a half delay,鈥 Robbins said. 鈥淭here鈥檚 no doubt about it.鈥
The city auditor’s office didn鈥檛 see the same pushback from Robbins as it did from Grabauskas nearly three years ago — likely because much of the report covers HART before Robbins arrived.
But Robbins and the city auditor still disagree on key issues. HART maintains that it鈥檚 already taken action on all 16 of the auditor鈥檚 recommendations from 2016.
鈥淲e feel like we鈥檝e addressed just about all of those,鈥 Robbins said Friday.
The auditor disagrees.
HART still 鈥渘eeds to demonstrate not only that it has established policies, procedures and plans that address the recommendations, but that they are actually being implemented and making an impact,鈥 the report stated.
Until then, the project remains vulnerable to more cost increases, it added.
Robbins said the auditor staff will continue to visit HART鈥檚 offices in the coming year to see whether the steps taken are actually working. 鈥淲e鈥檙e fine with that,鈥 he said.
More reports on rail from the state auditor are expected to be released in the coming weeks.
Read the city auditor’s report here:
GET IN-DEPTH REPORTING ON HAWAII鈥橲 BIGGEST ISSUES
Support Independent, Unbiased News
Civil Beat is a nonprofit, reader-supported newsroom based in 贬补飞补颈驶颈. When you give, your donation is combined with gifts from thousands of your fellow readers, and together you help power the strongest team of investigative journalists in the state.
About the Author
-
Marcel Honor茅 is a reporter for Civil Beat. You can email him at mhonore@civilbeat.org