Honolulu Mayor Kirk Caldwell would like some answers, please.

After receiving a letter 10 days ago from the board chair and executive director of the detailing more than $200 million in potential additional rail cost overruns and a likely one-year delay in the project鈥檚 completion, he replied to both leaders with a letter pointedly asking for details in six areas.

Principal among his concerns seems to be that the Sept. 14 letter sent by Board Chair Don Horner and Executive Director Dan Grabauskas differs from information the project provided last spring to legislators. HART and Caldwell sought and the Legislature passed a five-year extension of the .5 percent general excise tax surcharge funding the rail project.

Caldwell asked Horner and Graubaskas what information they obtained after the legislative session that led to the $200 million upward budget revision and the pushback of the 鈥渇inal Milestone date from January 2020 to the 鈥榤ore likely’ 2021 date?鈥

Mayor Kirk Caldwell held a press conference recently to discuss the Sept. 14 letter from HART leaders, saying he wanted to delve deeper into the details. Cory Lum/Civil Beat

The Sept. 14 letter pointed to a total of nine of 21 rail stations that have come in 鈥渁t or under budget鈥 鈥 three of them 鈥渨ell under.鈥 鈥淲hile this is encouraging news, the project鈥檚 construction over-budget number … remains at $594 million above original cost estimates included in our last budget update,鈥 the HART leaders wrote, adding that they project an additional $100 million in GET shortfalls, as well as a $210 million loss in Federal Transit Administration funding.

That total of nearly $910 million in cost overruns plus the potential $200 million in potential escalating costs from construction in the city’s core would push the project $1.1 billion into the red.

Caldwell asks Board Chair Horner and Executive Director Grabauskas what steps they could take to stick to the 2020 completion date 鈥 and what those steps might cost.

In his response, the mayor requests deeper detail regarding project costs or elements that are no longer part of HART鈥檚 budget assumptions. He also asks Horner and Grabauskas what steps they could take to stick to the 2020 completion date 鈥 and what those steps might cost.

He asks about the potential opening date for an interim, 15-mile phase featuring 13 stations between East Kapolei and Middle Street 鈥斅燼 section that would include Honolulu International Airport and Pearl Harbor. Opening that shorter segment early would allow the project to begin generating revenue and get people used to riding on the rail system.

Horner and Grabauskas said 73 percent of the land required to complete the entire project is now in hand, but Caldwell wants to know how much more land is needed to support the project鈥檚 鈥渕inimum operable segment鈥 and how revenue from that would compare to revenue from the 15-mile interim phase.

It鈥檚 a cordial letter, with Caldwell鈥檚 questions bracketed by praise for new project communications that are 鈥渢ransparent and forward thinking,鈥 for surpassing the four-mile mark in rail guideway construction and reaching 80 percent completion of the Rail Operations Center. The latter is particularly significant, given that rail cars are expected to be delivered to Honolulu in the first quarter of 2016.

But Caldwell also slips in a sentence seemingly to absolve himself of responsibility for incorrect or problematic information that may have been supplied during the legislative session, writing, 鈥淎ll substantive project information provided to the Legislature was provided by HART.鈥

Despite the fact that the Horner and Grabauskas letter was addressed to both Caldwell and Honolulu City Council Chair Ernie Martin, Caldwell鈥檚 reply went to Horner and Grabauskas only without even a “cc” for the council leader. A persistent Caldwell critic, Martin is thought to be preparing to challenge Caldwell when he stands for re-election next year.

Read Caldwell鈥檚 letter here:

from

Read the Sept. 14 letter from Horner and Grabauskas here: