Forget about the nearly $1 billion shortfall, Honolulu鈥檚 rail project has a cash flow problem that could halt work as soon as this summer.

Construction costs are now outpacing the money trickling in from taxes and the federal government. That means the Honolulu City Council must issue debt to temporarily cover the difference while the revenues catch up.

But council members are still uneasy about the plan, especially given the growing shortfall and the fact that state lawmakers have yet to pass an extension of the general excise tax surcharge to pay for it.

Honolulu’s rail project is over budget and facing a cash flow problem that could stop work.

Cory Lum/Civil Beat

On Wednesday, the City Council Budget Committee once again tabled an agreement with the Honolulu Authority for Rapid Transportation that would allow the city to .

Council members also signed off that would take $210 million in federal funds normally used for city bus service out of the rail budget, which effectively increases the shortfall and forces officials to find more money.

HART Executive Director and CEO Dan Grabauskas said these decisions add even more uncertainty to the project. The most immediate concern is cash flow.

Without bond revenues coming in, he said construction on the project could stop as soon as June unless contractors agree to get paid later, a sum that would likely include interest.

鈥淲e need the short-term borrowing to begin this summer,鈥 Grabauskas said. 鈥淚f we don鈥檛 have money we can鈥檛 pay our bills.鈥

The initial plan is to issue $350 million in debt to pay for ongoing construction in West Oahu. There鈥檚 currently enough money in the budget to pay back that debt.

But Grabauskas said the entire project is estimated to need a total of $1.9 billion in bond funding. The current budget can鈥檛 pay back that debt without a new funding source.

In fact, even with enough cash to cover current construction expenses and contracts the project is estimated to run out of money in the first quarter of 2016.

Council members were anxious about issuing debt in the face of such uncertainty. They said they would need a guarantee from the Legislature that the general excise tax would be extended beyond 2022.

The last thing they want to do is pay for the project using property taxes. Honolulu Mayor Kirk Caldwell has said those taxes would need to be increased by 30 percent to 40 percent to cover the current shortfall and operate the system.

鈥淥ur bottom line is the taxpayer. We really are worried,鈥 said City Councilwoman Ann Kobayashi, who chairs the Budget Committee. 鈥淲ho would give a loan to someone who has such a huge shortfall in their project and who has a questionable financial plan?鈥

Other council members said they didn鈥檛 want to make a decision on issuing debt until they know what the state plans to do. In essence, they said they didn鈥檛 want to get stuck with half a project.

There was much political grandstanding throughout Wednesday鈥檚 hearing, with council members and citizens berating HART for a lack of transparency and fiscal accountability.

At the same time, HART Chair Ivan Lui Kwan said it was important for the City Council to 鈥渟how some skin in the game鈥 with the Legislature to help move the project along and secure an extension on the GET.

Yet, underlying all these discussions is what to do about the Federal Transit Administration. The federal agency gave Honolulu $1.55 billion to build a 20-mile rail line with 21 stations.

The funding document included an agreement by the city to put up $210 million in federal bus money, known as 5307 funds, that are normally allocated to The Bus and Handi-Van.

But city officials, including council members and Caldwell, have made clear that those dollars are off limits, which puts HART in an awkward position.

Grabauskas said if he can鈥檛 find an additional $210 million to replace that money, the FTA could ask for a refund on the money that has been dished out and put the city in default.

鈥淭hat鈥檚 the extreme,鈥 he said.

Support Independent, Unbiased News

Civil Beat is a nonprofit, reader-supported newsroom based in 贬补飞补颈驶颈. When you give, your donation is combined with gifts from thousands of your fellow readers, and together you help power the strongest team of investigative journalists in the state.

 

About the Author